Weight Stiffness Case study

Boom lift, 29 m, 100 kg lighter

The customer operates an 18 m-class aerial work platform on a blue-plate chassis (China's light-truck category, with a hard cap on gross vehicle weight). The requirement: a working height above 26 m.

With steel, the two requirements cannot both be met. The boom is a cantilever: bending moment grows with the square of its length, while self-weight grows linearly, and self-weight is itself deducted from payload. Adding material does not buy height.

The original boom: six manganese-steel sections, 728 mm maximum deflection, 223 MPa maximum stress at rated load.

Original boom deflection contour
Original structure (six manganese-steel sections), displacement contour at 150 kg rated load with the boom fully extended.

Approach

A pure composite boom does not work either. Bearing strength and wear resistance at the pin bores fall well short of those of steel, and the boom joints cannot carry the load.

The final design uses eight sections with a U-shaped cross-section. At the same section depth, a U-section bends more efficiently and leaves room to seat wear pads between sections.

Material is graded to the bending moment: high-strength steel at the root; carbon fibre and high-strength steel together through the middle sections; and pure carbon fibre in the smallest tip section. Bending moment falls from root to tip, and material strength falls with it, so the most expensive material sits only where the load is lowest.

The first build kept the original six sections and changed only the material.

Six-section steel-carbon hybrid, same load case and same scale for direct comparison.

Verification and Iteration

The first strength check was done by an intern, and the result looked unusually good: he believed the boom could reach 40 m. At the design review, a colleague pointed out that the check had omitted the boom's own weight. In a cantilever, that is fatal — self-weight is a primary source of bending moment, so omitting it is equivalent to counting the largest load as zero.

Iteration followed: new forming processes, adjusted steel wall thickness, different carbon fibre grades, and a fresh strength check on every version, with the customer involved throughout.

Results

Six-section steel-carbon hybrid, boom length unchanged at 22 m: deflection rose from 728 mm to 768 mm, just 40 mm more, for 300 kg less weight.

Eight-section, 29 m boom: maximum stress 333 MPa, maximum deflection 1460 mm, meeting GB 25849-2010.

Two more sections take the boom from 22 m to 29 m, a 32% increase, and lift the machine from the 18 m class to a working height above 26 m. The boom still weighs 100 kg less than the original six-section steel boom. The two added sections cost 200 kg.

Eight-section boom stress contour
Maximum stress contour for the eight-section boom. Peak stress sits at the root and the pin bores — the two places worth checking first.

Doubling the deflection was unavoidable at that length. It remains within the deflection the standard allows.

Send the drawing. We will send the route.

A drawing, a photo of a failed part, or three lines of requirement is enough to start. Scope, price indication and lead time within 24 hours.

No commitment · NDA available · Reply within 24 hours

Request a quote WhatsApp